PORT MORESBY — Six days before a key licence over Papua LNG expires, the country’s leaders cannot agree on whether the date matters at all.
Shadow Petroleum and Energy Minister Kerenga Kua told a press conference on Friday that the project was days away from collapse unless the Government signs a development agreement with project-area stakeholders before Petroleum Retention Licence 15 lapses on 30 November. Without that agreement, he argued, the minister cannot lawfully issue a petroleum development licence, and without the licence the developers cannot announce a final investment decision. He said Gulf provincial government and landowner representatives had boycotted the talks for weeks, NBC News reported.
Petroleum Minister Jimmy Maladina rejects that reading. In a statement on Sunday he said PRL 15 covers nine blocks, five of which hold identified gas and are covered by a pending application for a development licence. Under section 57(9) of the Oil and Gas Act, he said, tenure over those blocks continues while the application is decided. He noted the same provision was relied on during Mr Kua’s own time as minister to keep the P’nyang and Pasca projects alive.
On the development agreement, Mr Maladina said the Act requires the minister to convene a development forum and make a genuine effort to reach agreement, not to have a signed deal in hand. “The expiry of PRL 15 on Nov 30 does not mean the end of Papua LNG,” he said.
Why it matters
Papua LNG is the biggest new investment in the national pipeline and a pillar of the Government’s revenue plans for a balanced Budget. The partners, now led by ExxonMobil, are working towards a final investment decision deadline of 15 December. Even a tenure dispute the Government expects to win is the kind of risk that investment boards price in.
Our take
If the Minister is right on the law, there is no cliff edge on 30 November. But his argument does not answer the bigger problem Mr Kua points to: the Gulf landowners and provincial government are not at the table. A licence granted without their agreement may be lawful and still be hard to build on, as other resource projects have learned. The fastest way to settle the legal argument is to settle the landowner one.
The row also adds to pressure from the Opposition, which has been pressing the Government over the project for weeks.
What to watch
Whether talks with Gulf stakeholders resume before 30 November; any formal statement from the developers on tenure; and whether the 15 December investment decision holds.